plan [2022/03/15 17:33] – [Project Plan] team1plan [2022/06/08 12:29] (current) – [Deadlines] epsatisep
Line 10: Line 10:
   * 2022-04-14 Upload the **Interim Report and Presentation** to the wiki. The report must contain the the following chapters: Introduction, Project Management, State of the Art, Marketing Plan, Eco-efficiency Measures for Sustainability, Ethical and Deontological Concerns, Proposed Solution and Bibliography. In particular, the Project Management chapter includes the updated project progress register, the sprint report for completed sprints (tasks that were included, statuses, assignees, allocations) and the updated release Gantt chart    * 2022-04-14 Upload the **Interim Report and Presentation** to the wiki. The report must contain the the following chapters: Introduction, Project Management, State of the Art, Marketing Plan, Eco-efficiency Measures for Sustainability, Ethical and Deontological Concerns, Proposed Solution and Bibliography. In particular, the Project Management chapter includes the updated project progress register, the sprint report for completed sprints (tasks that were included, statuses, assignees, allocations) and the updated release Gantt chart 
   * 2022-04-21 Interim Presentation, Discussion and Peer, Teacher and Supervisor Feedbacks   * 2022-04-21 Interim Presentation, Discussion and Peer, Teacher and Supervisor Feedbacks
-  * 2022-04-27 Upload the final **List of Materials (local providers & price, including VAT and transportation)** to the wiki+  * 2022-04-27 Upload the final **List of Materials (local providers & price, including VAT and transportation)** and the **3D Model Video** to the wiki
   * 2022-05-14 Upload refined Interim Report (based on Teacher & Supervisor Feedback)   * 2022-05-14 Upload refined Interim Report (based on Teacher & Supervisor Feedback)
 +  * 2022-05-26 Upload **packaging solution** to Deliverables and Report
 +  * 2022-06-07 Upload the results of the **Functional Tests** to the wiki
   * 2022-06-07 Upload the results of the **Functional Tests** to the wiki   * 2022-06-07 Upload the results of the **Functional Tests** to the wiki
   * 2022-06-18 Upload the **Final Report, Presentation, Video, Paper, Poster and Manual**   * 2022-06-18 Upload the **Final Report, Presentation, Video, Paper, Poster and Manual**
Line 21: Line 23:
   * 2022-06-30:   * 2022-06-30:
     - Hand in the **prototype and user manual** to the client     - Hand in the **prototype and user manual** to the client
 +    - Do a **live demo** of the prototype
     - Receive the **EPS@ISEP certificate**     - Receive the **EPS@ISEP certificate**
-    - Bring **typical food** from your country+    - Bring and share **typical food** from your country
  
  
Line 54: Line 57:
 <WRAP box 400px center> <WRAP box 400px center>
 ^ PBI Sprint 0      ^ Title          ^ Status     ^ ^ PBI Sprint 0      ^ Title          ^ Status     ^
-        | Deadline: Define Project Backlog, Global Sprint, Intial Sprint Plan, Gantt Chart    | Done: DEADLINE      | +        | Deadline: Define Project Backlog, Global Sprint, Intial Sprint Plan, Gantt Chart    | Done: DEADLINE      | 
-| B         | State of the art     | To do      |    +| B         | State of the art - Scientific    | To do      |  
-        | Do research & decide which insects we are going to use    | To do      |       +C         | State of the art - Commercial    | To do      |   
-        | Do research & decide on which & how many differnt product outputs (pet feed, food, fertilizer) we want to produce    | To do      |    +| D         | Do research & decide which insects we are going to use    | To do      |       
-        | Do research on lifecycle options and present on possibilities    | To do      |    +        | Do research & decide on which & how many differnt product outputs (pet feed, food, fertilizer) we want to produce    | To do      |    
-        | Decide final idea     | To do      |    +        | Do research on lifecycle options and present on possibilities    | To do      |    
-        | Make System Diagrams    | To do      |    +        | Decide final idea     | To do      |    
-        | Make Structural Drafts    | To do      |    +        | Make System Diagrams    | To do      |    
-        | Deadline: Upload the “black box” System Diagrams & Structural Drafts to the wiki    | To do: DEADLINE      |+        | Make Structural Drafts    | To do      |    
 +        | Deadline: Upload the “black box” System Diagrams & Structural Drafts to the wiki    | To do: DEADLINE      |
 </WRAP> </WRAP>
 </table> </table>
Line 83: Line 87:
 </WRAP> </WRAP>
  
-Plan each sprint at its beginning (Sprint Planning session) using the Sprint Plan Table {{ref>tlabel3}}.+Plan each sprint at its beginning (Sprint Planning session) using the Sprint Plan Table 
 +F=Finn 
 +B=Benjamin 
 +L=Leonie 
 +P=Paul 
 +M=Marie 
 + {{ref>tlabel3}}.
 <WRAP centeralign> <WRAP centeralign>
 <table tlabel3> <table tlabel3>
Line 89: Line 99:
 <WRAP box 400px center> <WRAP box 400px center>
 ^ Sprint    ^ Task  ^  Duration (d) ^  Responsible ^ Involved   ^ ^ Sprint    ^ Task  ^  Duration (d) ^  Responsible ^ Involved   ^
-        |     |             | and      XYZ|   +        |     |             | and      F, BLP|   
-        |     |             | Z            XYZ    +        |     |             | F,B and P    FBLP, M 
-        |     |             | W, Y and Z   XYZ+        |     |             | and M      FBLP, M     
-        |     | 1             Y            XYZ+        |     | 1              F, B, L, P, M  FBLP, M 
-| 5         | B                 | Z and W      XYZ|   +| 0         | E     | 5             |         | F, B, L, P, M | 
-        |     |             | X and W      XYZ+| 0         | F     |             |      | F, BLP|   
-        |     |             | Y and Z      XYZ|+        |     |             |      | FBLP, M 
 +        |     |             |       F, B, L, P, M | 
 +| 0         | I     | 3                   | F, B, L, P, M | 
 +| 0         | J     | 1                   | F, BLP|
 </WRAP> </WRAP>
 </table> </table>
Line 106: Line 119:
 <WRAP box 400px center> <WRAP box 400px center>
 ^ Sprint    ^ PBI   ^ Responsible  ^ Involved   ^ Status      ^ ^ Sprint    ^ PBI   ^ Responsible  ^ Involved   ^ Status      ^
-        |     | X and Y      XYZ| Done        |  +        |     |   M, L    F, BLP| Done        | 
-        | K     Z            XYZDone             +        | B, C  F, B, L, P, M    FBLP, M In progress        |  
-        | D     WY and Z   XYZDone        |  +        |                  | FB, L, P, M       |      
-        | A     Y            XYZDone        |  +| 2                     | FBLP, M         |  
-        | B     Z and W      XYZIn progress |   +        |             FBLP, M |        |  
-        | E     X and W      XYZIn progress +        |             FBLP, M  |   
-        | C     Y and Z      XYZIn progress |+        |             FBLP, M  
 +        |             FBLP, M  |
 </WRAP> </WRAP>
 </table> </table>
Line 125: Line 139:
 </WRAP> </WRAP>
  
 +===== Blackbox Diagram =====
  
 +
 +<WRAP centeralign>
 +<figure flabel1>
 +{{:blackbox_diagram_2.png|}}
 +<caption>Preliminary Blackbox Diagram</caption>
 +</figure>
 +</WRAP>
 +
 +===== Structural / Design Drafts =====
 +
 +
 +<WRAP centeralign>
 +<figure flabel1>
 +{{:design_draft_01.png|}}
 +<caption>Structural_Design_Draft</caption>
 +</figure>
 +</WRAP>